Evergreen Second Elementary School
Building & Modernizing Schools : Evergreen Second Elementary School
Skip Navigation LinksCBE Home Schools Building & Modernizing Schools Evergreen Second Elementary School

Building & Modernizing Schools

Evergreen Second Elementary School

2511 Fish Creek Boulevard SW

Anticipated Opening Date | September 2020
Grades | K-4

 

Mar. 19, 2019
Bird Construction has mobilized to site and construction will be getting underway. The Site Plan on the right-hand side of this page shows the footprint of the school on the site.

Construction Status

The construction status is updated using the Construction Projects Status Report.

 
Feb. 2019

Design and specifications​ ​100%
​Construction Award ​100%
​Construction Progress ​0%
Note: Project managed by Alberta Infrastructure. Contractor anticipated to mobilize to site in February 2019.
 

 
 

 Contact Us

 
 

 Provide Input

 

If you have any feedback that you would like to share with us, please fill out our online form.

 

 



 

 Supporting Documents

 
Last modified: 3/19/2019 11:18 AM
Website feedback: Webmaster
^