Construction Status
The construction status is updated using the Construction Projects Status Report, which is presented quarterly to the Board of Trustees.
Sept. 2024
Design Build – RFP Package ( includes drawing package to 30% development and Performance Specifications)
|
100% |
Design-Build Contract Award
|
100%
|
Design and Specifications
|
99% |
Construction Progress |
4% |
Note: Note: Project managed by Alberta Infrastructure. Design-build contractor mobilized to site in late April. Deep services installation underway, foundation work is complete, masonry work in progress.
|
|