Construction Status

The construction status is updated using the Construction Projects Status Report, which is presented quarterly to the Board of Trustees.​

​Sept. 2024

Design Build – RFP Package ( includes drawing package to 30% development and Performance Specifications) 
100%
​Design-Build Contract Award​
​100%
​Design and Specifications
​ 99%
​Construction Progress   4%
Note: Note: Project managed by Alberta Infrastructure. Design-build contractor mobilized to site in late April. Deep services installation underway, foundation work is complete, masonry work in progress.  
​​

​ ​​​​​​​​​​​​