Banner | McKenzie Highlands School

Archive

Archive McKenzie Highlands School

McKenzie Highlands School

25 McKenzie Towne Drive SE, Calgary AB T2Z 4B7

Community | McKenzie Towne 
Capacity | 900 students
Anticipated Opening Date | TBC
Grades | 5-8 (year 1); 5-9 (year 2)

Registration
School Website
Career Opportunities

 

Construction Status

The construction status is updated using the Construction Projects Status Report that is presented monthly to the Board of Trustees.

April 2017
 
Design and Specifications 100%
City Permits 100%
Construction Award 100%
Foundations 100%
Steel Fabrication and Erection 100%
Roofing and Membranes 100%
Building Envelope 100%
Interior Finishes 100%
 
March 2017
 
Design and Specifications 100%
City Permits 100%
Construction Award 100%
Foundations 100%
Steel Fabrication and Erection 100%
Roofing and Membranes 100%
Building Envelope 100%
Interior Finishes 95%
Note: Occupancy has been obtained. The school will open on March 6, 2017
 

Project Background

Summer 2015
  • After tender approvals by Alberta Infrastructure and the Board, a Letter of Award was issued to Maple Reinders. Mobilization and construction commenced. A partial Building permit was issued.

June 2015

  • Open House held to showcase proposed designation area, walk zone and grade configurations

March 2015

  • The Design-Build responses were unsatisfactory and over budget. The Design Team to finalize a new set of working drawings.

February 2015

  •  Lump sum tender documents issued for award
  • The development permit approved by the City

January 2015

  • Design-build proposal documents have been developed and are being reviewed prior to release

August 2014

  • Development permit application submitted

June 2014

  •  Open house held to showcase the design

February 2014

  • The Calgary Board of Education received approval from the Province of Alberta to build a new school in the community of McKenzie Towne.

2004 

  • McKenzie Towne Middle School was identified as a priority on the CBE Three-Year School Capital Plan

Design and Construction

  • Group 2 Architecture has been selected as Bridging Consultant.
  • Maple Reinders

Meet Your Principal | Kel Connelly

Maps

​Attendance Area



Walk Zone | Click the map below to view the walk zone for your school. To find out on how walk zones are determined and answers to frequently asked questions visit our school walk zone page.




 

Supporting Documents

​Jan. 2016 Community Engagement Plan
Dec. 15, 2015
Parent Feedback
​June 27, 2014 ​Site Map
​June 2014 Site Concept
 

 

Provide Input

If you have any feedback that you would like to share with us, please fill out our online form.

 

 

Dialogue Feedback Form​​
 
Last modified: 4/26/2017 1:04 PM
Website feedback: Webmaster
^