116 Brightondale Park SE, Calgary AB T2Z 0V1
Community | New Brighton/Copperfield
Capacity | 900 students
Anticipated Opening Date | March 2017
Grades | 5-8 (year 1); 5-9 (year 2)
RegistrationSchool WebsiteCareer Opportunities Construction Status
The construction status is updated using the Construction Projects Status Report that is presented monthly to the Board of Trustees.
April 2017
Design and Specifications |
100% |
City Permits |
100% |
Construction Award |
100% |
Foundations |
100% |
Steel Fabrication and Erection |
100% |
Roofing and Membranes |
100% |
Building Envelope |
100% |
Interior Finishes |
100% |
March 2017
Design and Specifications |
100% |
City Permits |
100% |
Construction Award |
100% |
Foundations |
100% |
Steel Fabrication and Erection |
100% |
Roofing and Membranes |
100% |
Building Envelope |
100% |
Interior Finishes |
95% |
Project Background
Summer 2015
- After tender approvals by Alberta Infrastructure and the Board, a Letter of Award was issued to Maple Reinders. Mobilization and construction has commenced. A partial Building permit has been issued.
June 2015
May 2015
March 2015
- The development permit application was approved by the City.
February 2014
- The Calgary Board of Education received approval from the Province of Alberta to build a new school in the community of New Brighton.
2010
- New Brighton Middle School was identified as a priority on the CBE School Three-Year Capital Plan.
Design and Construction
- Bridging Consultant - Group 2 Architecture
- Construction - Maple Reinders