Hugh A. Bennett School

​40 Saddlelake Way NE (tentative)

Community | Saddle Ridge 
Capacity | 600 Students 
Anticipated Opening Date | Dec. 2016
Grades | K-4

Kindergarten registration will take place at our new school starting Jan. 9, 2017.

Registration
School Website
Career Opportunities

School Opening Update

The school is now open.

Construction Status

The construction status is updated using the Construction Projects Status Report that is presented monthly to the Board of Trustees.

January 2017
 
Design and Specifications 100%
City Permits 100%
Construction Award 100%
Foundations 100%
Steel Fabrication and Erection 100%
Roofing and Membranes 100%
Building Envelope 100%
Interior Finishes 100%
 

December 2016

Design and Specifications 100%
City Permits 100%
Construction Award 100%
Foundations 100%
Steel Fabrication and Erection 100%
Roofing and Membranes 100%
Building Envelope 100%
Interior Finishes 100%
Note: The construction is complete, and occupancy has been granted. The school will open Dec. 5, 2016.  

 

November 2016

Exterior cladding is complete. Roofing installation is complete. Slabs on grade are complete. Wall, floor and ceiling installation are complete. Progress on site continues with landscaping completed. Construction is on schedule.

Design and Specifications 100%
City Permits 100%
Construction Award 100%
Foundations 100%
Steel Fabrication and Erection 100%
Roofing and Membranes 100%
Building Envelope 95%
Interior Finishes 95%
Note: N/A  

Project Background

September 2015

  • After tender reviews and approvals by Alberta Infrastructure and the Board, a Letter of Award was issued to Bird Construction Group. Mobilization commenced at end of August. Awaiting approval for a Building Permit.

June 2015

  • An open house was held to showcase proposed designation areas, walk zones and grade configurations
  • Detailed design and tender documents were prepared for tender

February 2015

  • An Open House was held at the Education Centre for stakeholders to view design plans. 
  • The Province advised the CBE that the schools that were announced in October 2014 as starter schools would be funded for full construction.

October 2014

  • The Province committed to the immediate planning of the final school design

September 2014

  • The Calgary Board of Education received approval from the Province of Alberta to build a partial school in the community of Saddle Ridge.

2014

  • Saddle Ridge school was identified as a priority in the CBE 2015-2018 Three-Year School Capital Plan 

Design and Construction

  • Manasc Isaac Architects

  • Bird Construction Group 

 

Meet Your Principal | Lisa Nachtigal

Maps

​Saddle Ridge Attendance Area



Walk Zone | Click the map below to view the walk zone for your school. To find out on how walk zones are determined and answers to frequently asked questions visit our school walk zone page.






 

Announcements

Supporting Documents

​Jan. 2016 ​​Community Engagement Plan
​Dec. 15, 2015 Parent Feedback
​Oct. 17, 2014 Site Map
 

 

Provide Input

If you have any feedback that you would like to share with us, please fill out our online form.

 

 

Dialogue Feedback Form​​
 
Last modified: 1/17/2017 3:47 PM
Website feedback: Webmaster
^