40 Saddlelake Way NE (tentative)
Community | Saddle Ridge
Capacity | 600 Students
Anticipated Opening Date | Dec. 2016
Grades | K-4
Kindergarten registration will take place at our new school starting Jan. 9, 2017.
Registration School WebsiteCareer Opportunities School Opening Update
The school is now open.
Construction Status
The construction status is updated using the Construction Projects Status Report that is presented monthly to the Board of Trustees.
January 2017
Design and Specifications |
100% |
City Permits |
100% |
Construction Award |
100% |
Foundations |
100% |
Steel Fabrication and Erection |
100% |
Roofing and Membranes |
100% |
Building Envelope |
100% |
Interior Finishes |
100% |
December 2016
Design and Specifications |
100% |
City Permits |
100% |
Construction Award |
100% |
Foundations |
100% |
Steel Fabrication and Erection |
100% |
Roofing and Membranes |
100% |
Building Envelope |
100% |
Interior Finishes |
100% |
Note: The construction is complete, and occupancy has been granted. The school will open Dec. 5, 2016. |
|
November 2016
Exterior cladding is complete. Roofing installation is complete. Slabs on grade are complete. Wall, floor and ceiling installation are complete. Progress on site continues with landscaping completed. Construction is on schedule.
Design and Specifications |
100% |
City Permits |
100% |
Construction Award |
100% |
Foundations |
100% |
Steel Fabrication and Erection |
100% |
Roofing and Membranes |
100% |
Building Envelope |
95% |
Interior Finishes |
95% |
Note: N/A |
|
Project Background
September 2015
- After tender reviews and approvals by Alberta Infrastructure and the Board, a Letter of Award was issued to Bird Construction Group. Mobilization commenced at end of August. Awaiting approval for a Building Permit.
June 2015
- An open house was held to showcase proposed designation areas, walk zones and grade configurations
- Detailed design and tender documents were prepared for tender
February 2015
- An Open House was held at the Education Centre for stakeholders to view design plans.
- The Province advised the CBE that the schools that were announced in October 2014 as starter schools would be funded for full construction.
October 2014
- The Province committed to the immediate planning of the final school design
September 2014
- The Calgary Board of Education received approval from the Province of Alberta to build a partial school in the community of Saddle Ridge.
2014
- Saddle Ridge school was identified as a priority in the CBE 2015-2018 Three-Year School Capital Plan
Design and Construction
Manasc Isaac Architects
Bird Construction Group