483 Silverado Boulevard SW, Calgary AB T2X 2E2
Community | Silverado
Capacity | 600 Students
Opening Date | Nov. 20, 2017
Grades | K-5
School Website
Construction Status
The construction status is updated using the Construction Projects Status Report that is presented monthly to the Board of Trustees.
Nov. 2017
Design and Specifications |
100% |
City Permits |
100% |
Construction Award |
100% |
Foundations |
100% |
Steel Fabrication and Erection |
100% |
Roofing and Membranes |
100% |
Building Envelope |
100% |
Interior Finishes |
100% |
Note: School opened on Nov. 20, 2017. |
|
Oct. 2017
Design and Specifications |
100% |
City Permits |
100% |
Construction Award |
100% |
Foundations |
100% |
Steel Fabrication and Erection |
100% |
Roofing and Membranes |
100% |
Building Envelope |
95% |
Interior Finishes |
50% |
Note: School Opening set for Nov. 20, 2017. |
|
Project Background
- The contract was awarded to UPA Construction Group and construction has commenced on site.
May 2016
- Schematic Designs were developed. Tenders were received in March 2016 and have been approved by the Board of Trustees, and are being reviewed and assessed for approval by Alberta Infrastructure.
April 2016
- Working drawings and the pretender estimate were reviewed by Alberta Infrastructure for a tender release in January 2016. Tenders have been received and are being reviewed and assessed for approval by Alberta Infrastructure.
March 2016
February 2016
- Awaiting Alberta Infrastructure approval to tender.
December 2015
- Working drawings and the pretender estimate are being reviewed by Alberta Infrastructure for a tender release in January 2016
- Held open house at Education Centre for stakeholders to view design plans.
- Schematic designs have been developed.
- Steering committee meetings have commenced.
- Tenders were issued November 2014 and proposals were reviewed in December 2014.
- Design Services Contract was awarded to Sahuri + Partners Architecture Inc.
School Registration
Kindergarten registration starts on Jan. 9, 2017. Kindergarten registrations for Ron Southern School will be accepted at Ethel M. Johnson School. Please visit our Registering at a New School page for more information on how to register your child. We do not offer pre-registration or waitlists.
Current students who live within the new school's designation area and are currently attending Ethel M. Johnson School will automatically be transferred to the new school.
Student transfers from other CBE schools or other school districts will be accepted after the principal is in place, which will be at the beginning of April. Please check back after April 1, 2017 for more information on where to take student transfer forms.
We expect that the new school will have enough space for all of the students in its designation area.
Use our kindergarten calculator below to find out when your child can start kindergarten.
School Community
The school is anticipated to provide educational programming for students living in the community of Silverado. The school will provide instruction in the Regular Program.
School Facility
The school in Silverado will be built at Silverado Blvd SW & Silverado Way SW, on the approved CBE school site zoned for educational purposes.
Project Background
- March 31, 2015 - the Province committed to fully funding the construction of a school in Silverado.
- October 8, 2014 - the Province committed to the immediate planning and design of Silverado school.
- 2014 – Silverado was identified as a priority in the CBE Three-Year Capital Plan
Working with the Community
- You can provide feedback by clicking on the Your Voice Feedback Form
- We are committed to providing regular updates on this webpage