357 Tuscany Drive NW, Calgary AB T3L 3C9
Community | Tuscany
Capacity | 600
Anticipated Opening Date | Jan. 2017
Grades | K-3 (year 1); K-4 or K-5 (year 2)
Kindergarten registration will take place at our new school starting Jan. 9, 2017.
Registration School WebsiteCareer Opportunities Eric Harvey School Opening
This school is now open.
Construction Status
The construction status is updated using the Construction Projects Status Report that is presented monthly to the Board of Trustees.
January 2017
Design and Specifications |
100% |
City Permits |
100% |
Construction Award |
100% |
Foundations |
100% |
Steel Fabrication and Erection |
100% |
Roofing and Membranes |
100% |
Building Envelope |
100% |
Interior Finishes |
100%% |
Note: Landscaping is complete. Construction is substantially complete and occupancy is being sought. |
|
December 2016
Design and Specifications |
100% |
City Permits |
100% |
Construction Award |
100% |
Foundations |
100% |
Steel Fabrication and Erection |
100% |
Roofing and Membranes |
100% |
Building Envelope |
95% |
Interior Finishes |
95% |
Note: Landscaping is complete. Construction is substantially complete and occupancy is being sought. |
|
November 2016
The entire building is now watertight. Interior painting has commenced. Sprinkler system installation complete. Contractor continues to have challenges with the construction schedule. This project experienced significant weather related delays and manpower resource issues. Landscaping has commenced. Construction will be substantially complete by year end.
Design and Specifications |
100% |
City Permits |
100% |
Construction Award |
100% |
Foundations |
100% |
Steel Fabrication and Erection |
100% |
Roofing and Membranes |
90% |
Building Envelope |
90% |
Interior Finishes |
80% |
Note: N/A |
|
Project Background
Summer 2015
- A full building permit was approved.
May 2015
- Mobilization and construction commenced.
March 2015
The Design Team has finalized a new set of working drawings and lump sum Tender Documents were issued in March 2015. Tender closed in early April 2015.
February 2015
Design and Construction
- Bridging Consultant - Group 2 Architecture
- Everest Construction Management Ltd.