Archive

Archive Forest Lawn High School

Forest Lawn High School

​High School Grades 10-12 | Modernization

Expected Completion Date | Fall 2020

Questions & Answers

Information on the changes taking place at Forest Lawn High School including the modernization, Area 3 office and Chinook Learning (ELL/LINC).

Modernization Update

The construction status is updated using the Construction Projects Status Report that is presented to the Board of Trustees.

Sept. 2020
Phase One Design and Construction
100%
Phase Two Design and Specifications
​100%
​Phase Two Construction Award 100%
​Phase Two Construction Progress
​60%
​Note: Phase Two construction ongoing. Six classrooms have been completed and turned over to the school. One remaining classroom, four computer labs, and the learning commons will be turned over mid-December 2020.

Provide Input

If you have any feedback that you would like to share with us, please fill out our online form.

 

Dialogue Feedback Form​​
 
Last modified: 10/8/2020 9:40 AM
Website feedback: Webmaster
^