(Skyview Ranch Elementary/Middle School)
201 Skyview Ranch Road NE, T3N 2E7
Opened: April 2023
Grades | K-9
New School Updates
Mar. 30, 2023
Inform | Prairie Sky School Opening Date
It is happening! Prairie Sky School will be opening our doors on Monday, April 3, welcoming over 800 K-8 students for the remainder of the 2022-23 school year.
A heartfelt gratitude to all of the people who have contributed to building our school and to making it possible for us to open this year. We are excited to welcome students and families to our beautiful, bright school.
Please read the notice for full details and opening day information.
Mar. 24, 2023
Update | Prairie Sky School Opening Information
Over the past month, we have worked closely with Alberta Infrastructure to complete the school’s construction and set-up as quickly as possible. We are still optimistic that Prairie Sky School should be ready to welcome students on Monday, April 3, 2023.
We will provide confirmation next week once the final inspections have been completed. Principal Mona Harswinder Bains will email the opening date confirmation and a transition plan with school-specific details.
Please read the full notice for details.
Feb. 22, 2023Update | Prairie Sky School Construction Progress and Estimated Opening We are excited to share that construction on Prairie Sky School is progressing well, and we have identified a tentative opening date of Monday, April 3, after spring break.
We are cautiously optimistic about being able to welcome students on April 3 as there is still much that needs to be completed before this date. Parts of the school need to be completed, and the building must pass several inspections before the building is turned over for CBE use. We are working closely with Alberta Infrastructure to complete the work. We expect to confirm the opening date, transportation information, bell times and other details next month.
See the
full notice to read more.
Jan. 31, 2023Update | Prairie Sky School Construction Progress January 2023 Construction on Prairie Sky School is moving along well. We have not yet confirmed the opening date, but we are definitely getting close! Many of the outside finishings are almost complete, and the focus is now on getting the interior completed. This includes working on many of the specialty areas of the school such as the construction shop, science labs along with the foods and fashion rooms.
See the
full notice to read more.
Dec. 21, 2022Update | Prairie Sky School Construction Progress December 2022 Last month we promised we would provide an update on Prairie Sky School's construction progress. Construction by Alberta Infrastructure is continuing. We still, however, do not know when the school will be ready to welcome students.
A lot of work has been completed in the past month, with some areas of the school still being constructed. Our team was on site last week and reported that construction crews were working hard on the elementary side of the school, the main gym, the learning commons, hallways and some classrooms.
See the
full notice to view photos of the construction progress, in the areas mentioned.
Nov. 17, 2022
Update | Prairie Sky School Construction Progress November 2022
We know you are waiting for news about when Prairie Sky School will be open.
While we don’t yet have an opening date, we want to share a construction update with you. A lot of work has been completed since we last communicated with you in October. In the most recent Construction Project Status Report that was shared with the Board of Trustees on Oct. 11, the school’s construction was estimated to be 80 per cent complete. Our team was on site this week and reported that construction crews were working hard on the main gymnasium, the auxiliary gym, the learning commons, and a variety of classrooms.
Please see
the notice for more information and to view construction progress photos.
Oct. 26. 2022
Update | Prairie Sky School Construction Progress
Dear Parents/Guardians,
In September, we updated you on the expected construction timeline of Prairie Sky School.
In that letter, we also promised to provide an update on the school’s construction by the end of October. [Read More]
Sept. 16, 2022
Prairie School Construction Progress Update
Alberta Infrastructure recently informed the CBE that the school is expected to be completed and handed over to the CBE by the end of October. This date may change depending on how construction progresses and whether building inspections are completed.
Student safety is our top priority, and we must ensure that all preparations are in place before allowing students to enter the building. [Read More]
June 6, 2022
Inform | Prairie Sky 'School within a School' Update
Since the end of April, there has been a change in enrolment numbers for Prairie Sky School. Registrations for the school for the 2022-23 school year are higher than projected when we developed the 'school within a school' plan. While this is exciting because the Prairie Sky school community is growing, it presents challenges to the existing plan. [Read More]
May 11, 2022
We would like to share the Proposed Walk Zone for Prairie Sky School. [Read More]
Apr. 28, 2022
Inform | New School Opening in Skyview Ranch
The Calgary Board of Education (CBE) is pleased to be opening a new school in Skyview Ranch named Prairie Sky School. This school will serve all kindergarten to Grade 9 students in the Skyview Ranch community and allow them to attend a school closer to home. [Read More]
Mar. 31, 2022
Board of Trustees Names New School in Skyview Ranch
Prairie Sky School is the name of the new Calgary Board of Education elementary/middle school under construction in the northeast community of Skyview Ranch. The Board of Trustees approved the name for the school on March 29, 2022. [Read More]
Registration Information
Prairie Sky School will offer kindergarten to Grade 8 programming in 2022-23 and kindergarten to Grade 9 programming in 2023-24. Please reference the designation mapor our Find a School tool to confirm if Prairie Sky School is your designated school.
If your child is new to the CBE and you would like to register them, please reference our registration pages for instructions on how to register. If your child is currently attending a CBE alternative program or an out-of-attendance area school and you wish for them to be registered for Prairie Sky School, please review CBE’s transfer process and submit a transfer request form.
Construction Status
The construction status is updated using the Construction Projects Status Report that is presented quarterly to the Board of Trustees.
Jan. 2023
Design and Specifications |
100% |
Construction Award |
100% |
Construction Progress |
90% |
Note: Project managed by Alberta Infrastructure. Interior finishes ongoing, mechanical and electrical ongoing, exterior hardscapes completed, landscaping on hold until Spring.
|
|